We delivered the full fit-out of a vacant unit within the Oracle shopping centre in Reading.  This included new walls, ceilings, electrical installation, mechanical installation, plumbing, flooring, raised access flooring, balustrades, tiling, decorations, new bar, fixed seating and joinery feature walls.  This was the first Hollywood Bowl to incorporate a sports bar area with multiple TV screens located within feature walls. 

A key challenge of this project was working within a fully operational shopping centre.  We worked closely with the shopping centre management team and all neighbouring businesses to minimise disruption during the works.  We worked within the confines of the shopping centre’s permit system, which required us to use a shared loading bay for deliveries and waste, with height restrictions and specific allocated timings.

We delivered the project to the original programme of 17 weeks, even with 2,500m2 of acoustic ceiling works added into the project, with no additional time allowed in the programme.